Data-Center Speed-to-Power War Game
A constraint and sequencing model connecting power, equipment, construction, commissioning, cooling, safety, and permitting dependencies to readiness and intervention priorities.
Synthetic dependency/scenario prototype
Task: Separate screened research-computing demand, dependency evidence and fallback cost assumptions before a readiness decision.
Contribution: Project direction by Kamal; AI-assisted implementation of an evidence-led extension alongside the original readiness and timeline lenses.
Inputs → processing → output: Synthetic capacity, stakeholder evidence and cost assumptions → ratio, freshness, dependency and fallback checks → review gates and wait-versus-fallback comparison.
Technology: React · Pure JavaScript evaluator · JSON schema + fixtures · Explicit cost arithmetic
What the reviewer can do: Change screened demand, capacity, dependency readiness or fallback cost; inspect recalculated ratios and explicit review issues.
Limits: Research-computing allocation scope. No commercial data-center forecast, validated stakeholder ranking, procurement approval, calibrated probability or realized outcome.
Try the inputs · Inspect implementation · View full case
What changes when you change an input?
Changing screened demand or available capacity recalculates their ratio. Changing queue wait or runtime recalculates the wait/runtime ratio. Dated evidence and dependency states update review flags; duration and cost assumptions recalculate the wait-versus-fallback comparison.
Computed: Demand/capacity and wait/runtime ratios; evidence freshness and gate flags; low, expected and high wait costs; fallback total and expected cost difference.
Published baseline: The original timeline/readiness lenses, charts and baseline figures above remain prepublished evidence. The new calculations do not rewrite them.
Scoped to research-computing allocation. Inputs, thresholds and ordering are synthetic design assumptions. Evidence completeness is not purchase approval; qualitative confidence is not a probability.